Project Address: 2420 Yarnell Rd, Henrico VA 23231
Most of the tasks on this project are fairly easy and we will provide help as necessary. Phases 3 & 4 are mostly done. Materials will be provided.
Tentative Timeline
Phase | Line Item | Start | Labor | Deposit | Final | Lead Required |
---|---|---|---|---|---|---|
3 | Rough Plumbing | 4/21 | $750.00 | $250.00 | $500.00 | Helpers |
3 | Rough Electrical | 4/21 | $400.00 | $133.34 | $266.66 | Helpers |
3 | Rough Framing | 4/21 | $750.00 | $250.00 | $500.00 | Helpers |
3 | Roofing | 4/21 | $300.00 | $100.00 | $200.00 | Helpers |
3 | Siding | 4/21 | $1,500.00 | $500.00 | $1,000.00 | Crew |
4 | Gutters | 4/28 | $300.00 | $100.00 | $200.00 | Crew |
4 | Exterior Paint | 4/28 | $500.00 | $166.67 | $333.33 | Crew |
4 | Tile | 4/28 | $2,000.00 | $666.67 | $1,333.33 | Crew |
5 | Toilet | 5/5 | $720.00 | $240.00 | $480.00 | Crew |
5 | Insulation | 5/5 | $200.00 | $66.67 | $133.33 | Crew |
5 | Fixtures | 5/5 | $800.00 | $266.67 | $533.33 | Crew |
6 | Drywall Installation | 5/12 | $700.00 | $233.34 | $466.66 | Crew |
6 | Trim | 5/12 | $500.00 | $166.67 | $333.33 | Crew |
8 | Doors/Windows | 5/26 | $1,200.00 | $400.00 | $800.00 | Crew |
10 | Interior Paint | 6/9 | $2,000.00 | $666.67 | $2,000.00 | Crew |
12 | Flooring | 6/23 | $3,000.00 | $1,000.00 | $2,000.00 | Crew |
13 | Landscaping | 6/30 | $2,520.00 | $840.00 | $1,680.00 | Crew |
14 | Final Cleaning | 7/7 | $360.00 | $120.00 | $240.00 | Crew |