Project Schedule

Project Address: 2420 Yarnell Rd, Henrico VA 23231

Most of the tasks on this project are fairly easy and we will provide help as necessary. Phases 3 & 4 are mostly done. Materials will be provided.

Tentative Timeline

Phase Line Item Start Labor Deposit Final Lead Required
3Rough Plumbing4/21$750.00$250.00$500.00Helpers
3Rough Electrical4/21$400.00$133.34$266.66Helpers
3Rough Framing4/21$750.00$250.00$500.00Helpers
3Roofing4/21$300.00$100.00$200.00Helpers
3Siding4/21$1,500.00$500.00$1,000.00Crew
4Gutters4/28$300.00$100.00$200.00Crew
4Exterior Paint4/28$500.00$166.67$333.33Crew
4Tile4/28$2,000.00$666.67$1,333.33Crew
5Toilet5/5$720.00$240.00$480.00Crew
5Insulation5/5$200.00$66.67$133.33Crew
5Fixtures5/5$800.00$266.67$533.33Crew
6Drywall Installation5/12$700.00$233.34$466.66Crew
6Trim5/12$500.00$166.67$333.33Crew
8Doors/Windows5/26$1,200.00$400.00$800.00Crew
10Interior Paint6/9$2,000.00$666.67$2,000.00Crew
12Flooring6/23$3,000.00$1,000.00$2,000.00Crew
13Landscaping6/30$2,520.00$840.00$1,680.00Crew
14Final Cleaning7/7$360.00$120.00$240.00Crew

Final Payment is approx 5 business days from passing inspection